Get Application for Working Capital or Current Capital Sample


To,
Manager (FAVP)
Islami Bank Bangladesh Limited
Singair Branch, Manikganj.
Subject: Application for Working Capital or Current Capital.
Sir,
The sincere request with due respect is that we MAB Auto Bricks Ind. Ltd are regular customers of your branch and already we have been given booking 220.00 million taka in amount in Sanction No- IBBL/Singair/Inv on dated 23/08/2017 AD from your branch all of them have been used in project work. In that situation there has seen current capital for us. Therefore as per our production the description of current is given.
Daily production power is 150,000 piece
Serial No
Name and description of goods
Amount of raw products yearly
Fixed price
Measurement of of expenditure of raw goods yearly in total
01.
Soil= 20625 CFT including 10%  wastage rate
74,25,000/- CFT
12/- taka per litre
8,91,00,000
02.
Coal= 40 ton including 5% wastage rate
14,400 ton
13500.00 Taka
194400,000
03.
Electricity/ generator

0.55 taka
2,97,00,000
Total:
31,32,00,000

Expenditure will be for 90 days= 7,83,00,000/- only.
As per the account mentioned above the project is needed for current capital. At present the work of the project is about the level of ending. We will start producing bricks on the next 1st April, 2018 AD as per progress of the project. As we are wanting to start production in the month of April in that we will have to start raw materials from from now. And there is needed current capital for collecting raw materials. Equity of current capital has already been invested in the project. As because of the reason equity has been invested of current capital which is as follows:
Continued to the Page No- 2
Page No- 2
1.     Total investment as per production is less and the amount of equity is more. The percentage of investment was 42% : 52%.
2.     There has been damaged in construction materials and construction work as because of much raining in the months of March and April in 2017 AD, which is constructed again.
3.     In case of the investment to change for the new supplier there is time consuming from the head office. As because of that reason the project work as is stopped for some days local and import cost of the project is increased.
4.     As the government specified the capacity of transportation load there is is spent additional taka too much in the transportation as well.
5.     As because of the reasons mentioned above there has invested in equity project of our current capital. As we are going to start in the month of April in that case now the necessary is to purchase advance coal and soil.
6.     Therefore, the sincere request to the sir is that, there is approved for withdrawn of 50% advance for making amassment soil and coal including booking taka of current capital.    

Thanking by
MAB, Auto Bricks Ind, Ltd.

No comments:

Post a Comment