Example Of Government Project Profile




BANGLADESH EXPORT PROCESSING ZONES AUTHORITY (BEPZA)                                                                                                                                                                            House no-19/D, Road-06, Dhanmondi, Dhaka –1206

MONTHLY REPORT
FOR
SUPERVISION& PROJECT MANAGEMENT CONSULTANCY
SUPERVISION FOR
CONSTRUCTION OF  FACTORY BUILDING’S AT ADAMJEE,COMILLA,MONGLA, ISHWARDI & UTTARA EPZ

FOR THE MONTH OF APRIL, 2015







 







PROKALPA UPODESHTA LTD
No: PUL/BEPZA/2015/                                                                                                                                                      Date: 05/05/2015
  To,
  The Chief engineer
  Bangladesh Export Processing Zones (BEPZA)
 House-19/D, Road -06, Dhanmondi, Dhaka-1206

Sub:    Monthly progress Report (April-2015)

Dear sir ,
 We are pleased to submit herewith the monthly progress report for the month of April 2015 for the  Construction of  Factory Building’s at Adamjee ,Comilla, Ishwardi, Mongla& Uttra EPZ For your kind perusal.


Thanking you,

Yours  faithfully
For   PROKALPA UPODESHTA LTD.

  ( MD. MANIRUZZAMAN)
          Team Leader 


CHAPTER-1

INTRODUCTION

1.0      BACKGROUN  INFORMATION
The objective of the project “Construction of Factory Building in EPZ under BEPZA” is to accelerate report growth and generation of employment through investment in EPZs of Bangladesh. To implement the objective of the project , it will be constructed two types  of multistoried standard factory buildings measuring approximately 3200 sqm plinth area in  Adamjee, Comilla, Ishwardi, Mongla, and 2830 sqm plinth area is Uttara EPZ. BEPZA will finance and will be responsible also for this assignment.

1.1    OBJECTIVE 
v  Full –time Supervision of Construction work of the 04 storied factory building having 8- storied foundation  at Adamjee, Comilla, Ishwardi, Mongla & Uttara EPZ.  Ensuring highest degree of quality in the construction work.
v  Monitoring and progress reporting to the Client
       
   1.2   SCOPE OF SERVICES
                   Major Scope of service of the consultant shall be :
v  Construction supervision for Quality control
v  Progress   Management including monitoring& Reporting.
v  Checking   & Certifying of payment Certificates.
v  Contract Closing activities including providing assistance in Dispute/ Claims Resolution/Arbitration, if any.
v  Preparation of Completion/ Taking over Certificates and Project Completion Report.
v  Preparation of Defect Liability Certificates.
v  Cooperation for permanent record and& documentation separately for the project.
v  Post- construction monitoring during12-month Defect maintenance period.
v  Assistance to and co- ordination with the client relating to execution of works.
v  Other supervision related tasks as deem fit to this context of construction.
 1.3    Scope of Physical facilities under the project
Package No.
                                               Works
  Unit
       Qty
           1
                                                   2
     3
         4

Construction of Multistoried Factory Buildings:



a)Mongla EPZ:


MMW-01
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Mongla EPZ  At Mongla EPZ
sqm
                1280.00
MMW-02
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Mongla EPZ
sqm
                1280.00
MMW-03
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Mongla EPZ
sqm
                1280.00

b) Ishwardi EPZ


MIW-01
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Ishwardi EPZ
sqm
                  1280.00
MIW-02
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Ishwardi EPZ
sqm
                  1280.00
MIW-03
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Ishwardi EPZ
sqm
                  1280.00

C) Uttara EPZ


MuW-01
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Uttara EPZ 
sqm
                1132.00
MUW-02
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Uttara EPZ
sqm
                1132.00
MUW-03
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Uttara EPZ
sqm
                1132.00
MUW-04

Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Uttara EPZ

sqm
1132.00

d) Comilla EPZ


MCW 01

Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Comilla EPZ


Sqm
1280.00
MCW 02

Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Comilla EPZ


Sqm
1280.00

e) Adamjee EPZ


MAW 01
Construction of 04 storied factory building having 8- storied foundation (MSSFB#1) At Adamjee. EPZ
Sqm
1280.00
MAW 02
Construction of 04 storied factory building having 8- storied foundation (MSSFB#2) At  Adamjee  EPZ
Sqm
1280.00
MAW 03
Construction of 04 storied factory building having 8- storied foundation (MSSFB#3) At Adamjee  EPZ
Sqm
1280.00

   1.4  The Consultant
 As per TOR  PROKALPA UPODESHTA LTD  was selected for consulting services for the  project  Updating/ preparing  construction
Design   of  Factory Building at Mongla, Ishwardi,  Comilla, Uttara& Adamjee Epz Unde   Bangladesh export processing zone authority (BEPZA)                                                          

  1.5 The  Contract:
 This CONTRACT " (hereinafter called the "Contract') is made the ...08.. day of the month December, 2014, between, on the one hand, Bangladesh Export Processing Zones Authority, House-19/D, Road-06, Dhanmondi, Dhaka-1206 (hereinafter called the "Client") and, on the other hand M/S.  Prokalpa Upodeshta Limited, House # 316, Block # B, Lalmatia, Dhaka-1207 (hereinafter called the "Consultant").















                                                                                            
CHAPTER-02

PROGRESS DURING THE MONTH

INTRODUCTION
We have been entrusted with the job of providing consultancy services  for supervision work  of construction work of 
Component- 1 construction of 4 storied factory building having 8- storied foundation (MSSFB# 1) at Adamjee EPZ.
Component- 2 construction of 4 storied factory building having 8- storied foundation (MSSFB# 2) at Adamjee EPZ.
Component- 3 construction of 4 storied factory building having 8- storied foundation (MSSFB# 3) at Adamjee EPZ
Component- 4 construction of 4 storied factory building having 8- storied foundation (MSSFB# 3) at Mongla EPZ
Component- 5 construction of 4 storied factory building having 8- storied foundation (MSSFB# 3) at Comilla EPZ
Component- 6 construction of 4 storied factory building having 8- storied foundation (MSSFB# 3) at Ishwardi EPZ
Component- 7 construction of 4 storied factory building having 8- storied foundation (MSSFB# 3) at Uttara EPZ
Component- 1 As agreement was  executed with  Hossain construction  Pvt  Ltd on 22  october 2014 for  Construction of 4 storied factory building having 8- storied foundation (MSSFB# 1) at Adamjee EPZ. The construction firm has already completed  pile casting , Pile driving work will be  started month of may 2015.
Component- 2 As agreement was HCPL & MHCL (Jv) on 17 Feb 2015 for construction of 4 storied factory building having 8- storied foundation (MSSFB# 2) at Adamjee EPZ. The construction farm arranged stone chips, sand & steel for casting test pile.  Test pile will be casted   08 may 2015.
Component- 3  The work is under tendering process.
Component- 4  The work is under tendering process.
Component- 5 The construction firm arranged Materials, equipment.  Contractors      site office & Engineer’s office. Pre-cast pile driving work will be started the next month.
Component-6)  The construction firm arranged Materials, equipment.  Contractors site office & Engineer’s office & completed test pile casting work.
Component-7)  Selection of contractor is going on.
2.1 CONSULTANTS  MOBILIZATION:
 On signing of contractor we have mobilize our field staff  simultaneously with the mobilization  by the  contractor .The  Consultant’s  build –up of the field staff have been graded and coincides with the notice to proceed and  start-up of construction  work by the contractors.
Before deployment to the sites , the consultant arrange an  orientation course for the supervision personnel  of the project team acquainting  them with the methodology and work plan of the project with a view  to  implementing the project in an effective and Efficient manner.

In consideration want of time the Authority is now intending to subdivide the whole services into 06 (six) groups. These are as follows-
SL. No
Name of the Phase
Remarks
01
Group- I
Consultancy services for preparation of architectural, structural (super structure), sanitary & plumbing, electrical & mechanical design drawings of two types of factory buildings (for two buildings only)

02
Group- II
Consultancy services for conducting sub-soil investigation and preparation of foundation design-drawing along with construction supervision of factory buildings at Mongla EPZ.
03
Group- III
Consultancy services for conducting sub-soil investigation and preparation of foundation design-drawing along with construction supervision of factory buildings at Ishwardi EPZ.
04
Group- IV
Consultancy services for conducting sub-soil investigation and preparation of foundation design-drawing along with construction supervision of factory buildings at Uttara EPZ.
05
Group- V
Consultancy services for conducting sub-soil investigation and preparation of foundation design-drawing along with construction supervision of factory buildings at Comilla EPZ.
06
Group- VI
Consultancy services for conducting sub-soil investigation and preparation of foundation design-drawing along with construction supervision of factory buildings at Adamjee EPZ


2.2 Time schedule for Professional personal
A  Schedule  of the  Consultants personnel  showing  involvement of each of them in terms of period  and  duration is present in Staffing schedule  Overall allocation and utilization of man – month  of different group  of professionals are also given in the bar-chart . The bar chart is presented in appendix –A.
2.3 Quality Control
  The quality control of materials and work, detailed  ,update and approved technical  specification s as per contract document  are being  strictly  flowing for all activities in the field . our field engineers are  ensuring  compliance of required specification before commencement of any actual work. With contractor’s mobilization, we are sampling basic construction materials ( Brick,  stone chips, cement, sand, rods, ms timber etc).   for laboratory test  through P W D in an approved  laboratory  preferably in material testing  laboratory of Bangladesh University of Engineering & Technology (BUET) for approval . All supplies for work  ensure to be  matched against approve sample kept as site  for the  propose . samples from  all fresh supply of materials  are being tested.
 Special  attention is being  given  to  concrete work . The contractor is required  to submit  mix design report s  and shop drawing  for shuttering  for approval  before  any  concrete work  commences. Concrete test  cylinders  are using  regularly for all major  casting as per contract,  curing procedures as required is  be strictly observed.
 Regular top supervision  from  head office by team leader  and senior engineer  are ensured  as  and when required  . They are also  cross-checking quality of work and materials being  used at the site . for further control  of quality of work in the field, our field engineer ‘s check –list of all major works . the test result are present in appendix-C











2.4 CONTRACTOR’S WORK PROGRAMME.
Upon issue  of work  order the contractor  ask to submit  detailed  mobilization plan, project management plan  construction schedule , site layout planet, for the site for the consultant ‘s  review  and  approval . This shall specifically include.
i)                    Review the contractor’s mobilization plan and oversee the implementation including recruitment of manpower, delivery of equipment, erection of temporary facilities demolition and cleaning.

ii)                  Review the contractor’s project management plan, quality control procedure mobilization plan to avoid delays and problems in the commencement of construction activities.

iii)                 Review and ultimately approve the contractor’s construction schedule.

iv)                Review and ultimately approve the contractor’s procurement schedule for local /imported materials and equipment on behalf of the client.

v)                  Verify that the contractor has at attained all standards referenced in the contractual specifications.

vi)                Verify that the contractor has submitted documents evidence of having obtained all insurance coverage and bank guarantees required by the contract.
vii)               Review that the contractor has secured all requisite permits prior to commencement of construction.

viii)             Review   contractor’s layout drawings of site including any temporary facilities and plant.

ix)                 Review contractor’s  proposals for provision of facilities  equipment and  procedures  for testing of materials  equipment  and systems  for  compliance with  control  documents.

x)                   Check that all copies of the contractor’s drawings and all other construction documents are identical to the signed contract document.

xi)                 Review and approve contractor’s project safety and security program.     
        