Example Of Government Project


3.1 Major Activity during the month at Adamjee

Ø  Mobilization Man Materials, equipment.
Ø  Contractors site office& Engineer’s office.
Ø  Pre-cast pile drive work


A.    MATERIALS STATEMENT

ITEM
RECEIVED
USED
BALANCE
1 .M S ROD
430.15 Ton
428.00 ton
3.15 ton
2. Cement (mir brand)
22800 bags
22500 bags
300 bags
3.Stone chips
89830 cft
89500 cft
330 cft
4. Sylhet sand
44900 cft
44500 cft
400 cft
5. Local sand
5000 cft
4500 cft
500 cft
6. Fine sand
2500 cft
2200 cft
300 cft
7. Bricks
60000 nos
45000 nos
15000 nos





4.1 Major Activity during the month at Comilla

Ø  Mobilization Man, Materials, equipment.
Ø  Contractors site office& Engineer’s office.
Ø  Pre-cast pile driving work

A.    MATERIALS STATEMENT

ITEM
RECEIVED
USED
BALANCE
1 .M S ROD
265.50 Ton
260.00 ton
5.00 ton
2. Cement Crown  brand)
14250 bags
14050 bags
200 bags
3.Stone chips
55600 cft
55300 cft
300 cft
4. Sylhet sand
18500 cft
18300 cft
200 cft
5. Local sand
4000 cft
3000 cft
1000 cft
6. Fine sand
2500 cft
2000 cft
500 cft
7. Bricks
50000 nos
45000 nos
5000 nos


5.1 Major Activity during the month Ishwardi

Ø  Mobilization Man, Materials, equipment.
Ø  Contractors site office& Engineer’s office.
Ø  Test pile casting  work

A.    MATERIALS STATEMENT

ITEM
RECEIVED
USED
BALANCE
1 .M S ROD
4.80 Ton
2.80 ton
2.00 ton
2. Cement (mir brand)
600 bags
500bags
100 bags
3.Stone chips
880 cft
480 cft
400 cft
4. Sylhet sand
650 cft
350 cft
300 cft
5. Local sand
5000 cft
4500 cft
500 cft
6. Fine sand
2500 cft
2200 cft
300 cft
7. Bricks
45000 nos
40000 nos
10000 nos








Name of work :         Construction of Multi storied factory building  at Adamjee,
Comilla, Ishwardi EPZ

Progress report
For
The month of april,2015

SUMMARY SHEET

Name of works
Name
of Contractor
Contract Value (Tk. In Lac)
Progress in % Previous Month
Up to date
Total
Physical
Financial
Physical
Financial
Physical
Financial