Sub: Estimate for conversion of Gas firing system of your Boiler/Generator for 4¢¢ dia Service line (Three One Kilometer) Long.

Part-A:    Cost of materials to be purchased from Bakhrabad Gas Store existing line to the outlet of the matter. The rates are approximate and subject to Bakhrabad ex-store price and demand note.

Sl. No.
Name of items
Quantity
Unite Price
Amount
01
4¢¢ M.S Pipe API Gr. B/Erw
3.1 Km 4’’ Dia Pipe


02
4¢¢ Flange valve Class AS/AP 150 R/F (Mild Steel)
5 No


03
4¢¢ Flange Class AS/AP 150 R/F (Mild Steel)
10 No


04
4¢¢ Gaskit Class 150/RF
16 No


05
3¢¢×5/8¢¢ Stud nut- bolts with washers etc.
Text Box: All material pushes for Bakhrabad Gas System Ltd pay for service line demand note72 No


06
4¢¢×4¢¢×4¢¢ Valve Tee (Service tee)
1 No


07
4¢¢×900 elbow welded
10 No


08
1¢¢ M.S. Socket /Plug
4 No


09
400¢×4¢¢ Tape (Policon)
2000 Roll


10
Primer (Policon)
48 Litter


11
M.S. Valve Pit cover
5 No


12
4¢¢ Insulating Joint (Electric Proof)
1 No


13
8¢¢ Dia 10mm Sickness Kasing Pipe
300 Fit



N.B: The rate of above items may very as per Bakhrabad specification.
Contd. P/2


-2-

Part-B:    Cost of materials to be purchased 70/20 PSI Gas line materials from the outlet of the meter to different utilization points (May be supplied by the Customer) the materials to be Bakhrabad specification. 

MAY BE SUPPLIED BY THE CUSTOMER:
01
4¢¢, 6¢¢ & 8¢¢ M.S Pipe API 5 L Gr. B. Erw



02
4¢¢, 6¢¢ & 8¢¢ Flange valve complete with flange, gaskit, nut, bolts, washers etc. S/P 150 R/F



03
4¢¢ Flange valve (Made of Mild Steel)
Text Box: Cost may be 6,00,000/-


04
4¢¢, 6¢¢ & 8¢¢×900 Elbow (M.S) wealday



05
4¢¢×400¢ Tape (policon)



06
M.S. fitting, elbow Gas valve etc. fitting



07
Except the above materials if any item required at the time of work the owner will arrange to supply the same as per requirement without loss of time




Part-C:    Cost of labour charge against Part-A 4¢¢ & 8¢¢ 3.1 Kilometer Long (Bakhrabad Existing Line) and Part- B (Internal line) House Line. 

01
Laying of pipe complete with trench cutting Bakub & Labor, Pucca/RCC cutting, cleaning, costing, wrapping for tap, normal back filling etc. as per specification of Bakhrabad Gas Co. for 4¢¢ & 8¢¢ 3.1 Kilometer Long  Dia Pipe



Contd. P/3


-3-

Sl. No.
Name of items
Quantity
Unite Price
Amount
02
Welding charges of the following:
a) 4¢¢, 6¢¢, 8¢¢ Saddle Weld 3.1 kilometer long dia pipe .


Average
80,00,000/-


03
Installation charges of the following:
a) 4¢¢×4¢¢×4¢¢ Valve tee (flange tee) and fitting
b) 4¢¢ Flange valve fitting & welding  5 No


04
Cost of conversion design.


05
Cost of road cutting permission from road & highway and road boring  (permission collect by owner of customer)

Collect For Customer
06
Purging/Testing with Nitrogen gas or air to meet the safety rules of Bakhrabad Gas, Recorder Flange 3.1 kilometer long

07
Construction of Pucca /RCC valve inspection pit complete with all required materials like bricks, M.S Rod, Cement, Khoa, Sand etc. including excavation etc. as per specification of Bakhrabad Gas Co.
5 Job

08
Overall service charges and office expenses, meter fitting, R.M. fitting & diling  etc. complet office & 60 Working etc.


09
Cost of carrying charges from Bakhrabad to your work site (Truk & Lory)
                                       
10
May be supply 100 truk Viti Balu working for pipe



Total Labour Cost. Part- C
72,50,000/-

Grand Total:
Part- A             : Cost of pipe line material demand not pay for Bakhraba Gas Office
Part- B : Internal material supply for customer           
Part- C : Cost of labor Charge Part- A, Part- B & Part- C,  All working &
   Labour charge & office cost etc.                  Tk. 72,50,000/-                       
                                                                                    Tk. 72,50,000/-
In Word: Seventy Two Lac Fifty Thousand Only.

Contd. P/4

-4-
Terms and Conditions:

01.  All the works will be carried out as per Bakhrabad Specification and direction.
02.  The above quantities are approximate and subject to actual work basis.
03.  40%  advance to be paid by the owner against Labour charge at the time of signing of the Agreement.
04.  4 month time to be required for completion of the works after approval by the Bakhrabad Office.
05.  Bakhrabad Gas Co. pay to security money to be customer deposited as 1/3rd cash and 2/3rd by Bank guarantee 5 year as per Bakhrabad Gas System Ltd & Law.