To
The
Managing Director
Robin
Printing & Packing Ltd
Gazipur,
Dhaka.
Sub: Estimate for conversion of Gas firing system of your Boiler for 2¢¢ dia Service line
Part-A:
Cost of materials to be purchased from Titas
Gas Store existing line to the outlet of the matter. The rates are approximate
and subject to Titas ex-store price and demand note.
Sl. No.
|
Name of items
|
Quantity
|
Unite Price
|
Amount (Tk.)
|
01
|
2¢¢ M.S
Pipe API Gr. B/Erw
|
16
meter
|
850
P. meter
|
13,600/-
|
02
|
2¢¢
Flange valve Class AS/AP 150 R/F (Mild Steel)
|
2 No
|
14,000
P. Pcs
|
28,000/-
|
03
|
2¢¢
Flange Class AS/AP 150 R/F (Mild Steel)
|
4 No
|
850
P. Pcs
|
1,700/-
|
04
|
2¢¢
Gaskit Class 150/RF
|
4 No
|
150
P. Pcs
|
300/-
|
05
|
3¢¢×5/8¢¢ Stud
nut- bolts with washers etc.
|
16 No
|
80 P.
Pcs
|
1,280/-
|
06
|
2¢¢×2¢¢×2¢¢
Valve Tee (Service tee)
|
1 No
|
12,000
P. Pcs
|
12,000/-
|
07
|
2¢¢×900
elbow welded
|
4 No
|
180
P. Pcs
|
720/-
|
08
|
1¢¢ M.S.
Socket /Plug
|
2 No
|
60 P.
Pcs
|
120/-
|
09
|
200¢×2¢¢ Tape
(Policon)
|
2
Roll
|
1,200
P. Roll
|
2,400/-
|
10
|
Primer (Policon)
|
2
Litter
|
400
P. Litter
|
800/-
|
11
|
M.S. Valve Pit cover
|
2 No
|
12,000
P. Pcs
|
24,000/-
|
12
|
2¢¢
Insulating Joint (Electric Proof)
|
1 No
|
7,000
P. Pcs
|
7,000/-
|
Total
=
|
91,920/-
|
N.B:
The rate of above items may very as per Titas Gas Company Ltd specification.
Contd.
P/2
-2-
Part-B:
Cost of materials to be purchased 150/10
PSI Gas line materials from the outlet of the meter to different utilization
points (May be supplied by the Customer) the materials to be Titas
specification.
MAY
BE SUPPLIED BY THE CUSTOMER:
|
||||
01
|
3¢¢ M.S
Pipe API 5 L Gr. B. Erw
|
1200
Fit
|
400
P. Pcs
|
4,80,000/-
|
02
|
2¢¢ Flange
valve complete with flange, gaskit, nut, bolts, washers etc. S/P 150 R/F
|
3 No
|
12,000
P. Pcs
|
36,000/-
|
03
|
3¢¢
Flange (Made of Mild Steel)
|
6 No
|
300
P. Pcs
|
1800/-
|
04
|
3¢¢, 2¢¢ ×900
Elbow (M.S) wealday
|
12 No
|
400
P. Pcs
|
4800/-
|
05
|
M.S. fitting, elbow Gas valve etc. fitting
|
L. S
|
L.S
|
20,000/-
|
07
|
Except the above materials if any item required at
the time of work the owner will arrange to supply the same as per requirement
without loss of time
|
|
|
|
Total=
|
5,42,600/-
|
Part-C:
Cost of labour charge against Part-A (Titas
Existing Line) and Part- B (Internal line) House Line.
01
|
Laying of pipe complete with trench cutting, Pucca/RCC
cutting, cleaning, coating, wrapping, normal back filling etc. as per
specification of Titas Gas Co. for 2¢¢
& 3¢¢ Dia Pipe 1260¢
|
1260 Fit
|
250 P. Fit
|
3,15,000/-
|
Contd.
P/3
-3-
Sl. No.
|
Name of items
|
Quantity
|
Unite Price
|
Amount
|
02
|
Welding charges of the following:
a) 2¢¢, 3¢¢
Saddle Weld
|
70 No
|
450 P. Pcs
|
3,15,000/-
|
03
|
Installation charges of the following:
a) 2¢¢×2¢¢×2¢¢
Valve tee (flange tee) and fitting
|
1 No
|
5000 P. Pcs
|
5000/-
|
b) 2¢¢
Flange valve fitting & welding 3
No
|
3 No
|
4500 P. Pcs
|
13,500/-
|
|
04
|
Cost of conversion design.
|
L. S
|
L. S
|
10,000/-
|
05
|
Cost of road cutting permission from road &
highway and road boring (permission
collect by owner of customer)
|
L. S
|
L. S
|
85,000/-
|
06
|
Purging/Testing with Nitrogen gas or air to meet
the safety rules of Titas Gas Company Ltd.
|
L. S
|
L. S
|
35,000/-
|
07
|
Construction of Pucca /RCC valve inspection pit
complete with all required materials like bricks, M.S Rod, Cement, Khoa, Sand
etc. including excavation etc. as per specification of Titas Gas Co.
|
2 Job
|
30,000
|
60,000/-
|
08
|
Overall service charges and office expenses, meter
fitting, R.M. fitting & diling
etc. complet.
|
L. S
|
L. S
|
1,75,000/-
|
09
|
Cost of carrying charges from Titas to your work
site
|
L. S
|
L. S
|
8,000/-
|
Total
Labour Cost. Part- C =
|
7,38,000/-
|
|||
10
|
Collect boiler certificate
|
L. S
|
85,000/-
|
|
Total
=
|
8,23,000/-
|
Grand
Total:
Part-
A : Titas existing line pay
demand note Tk. 91,920/-
Part-
B : Internal material costing Tk. 5,42,600/-
Part-
C : Labour Cost Part A & Part B etc. Tk.
8,23,000/-

In
Word: Fourteen Lac Fifty Seven Thousand Five Hundred Twenty Only.
Contd.
P/2
-4-
Terms
and Conditions:
01. All
the works will be carried out as per Titas Specification and direction.
02. The
above quantities are approximate and subject to actual work basis.
03. 50% advance to be paid by the owner against
Labour charge at the time of signing of the Agreement.
04. 3
month time to be required for completion of the works after approval by the Titas
Office.
05. Titas
security money to be deposited as 1/3rd cash and 2/3rd by
Bank guarantee as per Titas Gas System Ltd.
With
thanks and best regards,
Yours
faithfully
For: Bari
Enterprise
(Al-Haz Md. Ibrahim Khalil)