Example Of Pricing From Robin Printing & Packing


To
The Managing Director
Robin Printing & Packing Ltd
Gazipur, Dhaka.

Sub: Estimate for conversion of Gas firing system of your Boiler for 2¢¢ dia Service line

Part-A:    Cost of materials to be purchased from Titas Gas Store existing line to the outlet of the matter. The rates are approximate and subject to Titas ex-store price and demand note.

Sl. No.
Name of items
Quantity
Unite Price
Amount (Tk.)
01
2¢¢ M.S Pipe API Gr. B/Erw
16 meter
850 P. meter
13,600/-
02
2¢¢ Flange valve Class AS/AP 150 R/F (Mild Steel)
2 No
14,000 P. Pcs
28,000/-
03
2¢¢ Flange Class AS/AP 150 R/F (Mild Steel)
4 No
850 P. Pcs
1,700/-
04
2¢¢ Gaskit Class 150/RF
4 No
150 P. Pcs
300/-
05
3¢¢×5/8¢¢ Stud nut- bolts with washers etc.
16 No
80 P. Pcs
1,280/-
06
2¢¢×2¢¢×2¢¢ Valve Tee (Service tee)
1 No
12,000 P. Pcs
12,000/-
07
2¢¢×900 elbow welded
4 No
180 P. Pcs
720/-
08
1¢¢ M.S. Socket /Plug
2 No
60 P. Pcs
120/-
09
200¢×2¢¢ Tape (Policon)
2 Roll
1,200 P. Roll
2,400/-
10
Primer (Policon)
2 Litter
400 P. Litter
800/-
11
M.S. Valve Pit cover
2 No
12,000 P. Pcs
24,000/-
12
2¢¢ Insulating Joint (Electric Proof)
1 No
7,000 P. Pcs
7,000/-
Total =
91,920/-

N.B: The rate of above items may very as per Titas Gas Company Ltd specification.
Contd. P/2


-2-

Part-B:    Cost of materials to be purchased 150/10 PSI Gas line materials from the outlet of the meter to different utilization points (May be supplied by the Customer) the materials to be Titas specification. 

MAY BE SUPPLIED BY THE CUSTOMER:
01
3¢¢ M.S Pipe API 5 L Gr. B. Erw
1200 Fit
400 P. Pcs
4,80,000/-
02
2¢¢ Flange valve complete with flange, gaskit, nut, bolts, washers etc. S/P 150 R/F
3 No
12,000 P. Pcs
36,000/-
03
3¢¢ Flange (Made of Mild Steel)
6 No
300 P. Pcs
1800/-
04
3¢¢, 2¢¢ ×900 Elbow (M.S) wealday
12 No
400 P. Pcs
4800/-
05
M.S. fitting, elbow Gas valve etc. fitting
L. S
L.S
20,000/-
07
Except the above materials if any item required at the time of work the owner will arrange to supply the same as per requirement without loss of time



Total=
5,42,600/-

Part-C:    Cost of labour charge against Part-A (Titas Existing Line) and Part- B (Internal line) House Line. 

01
Laying of pipe complete with trench cutting, Pucca/RCC cutting, cleaning, coating, wrapping, normal back filling etc. as per specification of Titas Gas Co. for 2¢¢ & 3¢¢  Dia Pipe 1260¢
1260 Fit
250 P. Fit
3,15,000/-
Contd. P/3


-3-

Sl. No.
Name of items
Quantity
Unite Price
Amount
02
Welding charges of the following:
a) 2¢¢, 3¢¢ Saddle Weld
70 No
450 P. Pcs
3,15,000/-
03
Installation charges of the following:
a) 2¢¢×2¢¢×2¢¢ Valve tee (flange tee) and fitting
1 No
5000 P. Pcs
5000/-
b) 2¢¢ Flange valve fitting & welding  3 No
3 No
4500 P. Pcs
13,500/-
04
Cost of conversion design.
L. S
L. S
10,000/-
05
Cost of road cutting permission from road & highway and road boring  (permission collect by owner of customer)
L. S
L. S
85,000/-
06
Purging/Testing with Nitrogen gas or air to meet the safety rules of Titas Gas Company Ltd.
L. S
L. S
35,000/-
07
Construction of Pucca /RCC valve inspection pit complete with all required materials like bricks, M.S Rod, Cement, Khoa, Sand etc. including excavation etc. as per specification of Titas Gas Co.
2 Job
30,000
60,000/-
08
Overall service charges and office expenses, meter fitting, R.M. fitting & diling  etc. complet.
L. S
L. S
1,75,000/-
09
Cost of carrying charges from Titas to your work site
L. S
L. S
8,000/-
Total Labour Cost. Part- C =
7,38,000/-
10
Collect boiler certificate 
L. S
85,000/-
Total =
8,23,000/-

Grand Total:
Part- A             : Titas existing line pay demand note               Tk.      91,920/-
Part- B : Internal material costing                                 Tk.   5,42,600/-           
Part- C : Labour Cost Part A & Part B etc.                   Tk.   8,23,000/-                       
                                                                                    Tk. 14,57,520/-

In Word: Fourteen Lac Fifty Seven Thousand Five Hundred Twenty Only.

Contd. P/2

-4-
Terms and Conditions:

01.  All the works will be carried out as per Titas Specification and direction.
02.  The above quantities are approximate and subject to actual work basis.
03.  50%  advance to be paid by the owner against Labour charge at the time of signing of the Agreement.
04.  3 month time to be required for completion of the works after approval by the Titas Office.
05.  Titas security money to be deposited as 1/3rd cash and 2/3rd by Bank guarantee as per Titas Gas System Ltd.

With thanks and best regards,  

Yours faithfully
For: Bari Enterprise



(Al-Haz Md. Ibrahim Khalil)


No comments:

Post a Comment