To
The
Managing Director
Rahimafrooz,
West
Panisail, Zirani Bazar, Savar, 
Gazipur,
Bangladesh.
Sub:  Estimate for conversion of Gas firing system of your Generator &
Hit temper.  
Part-A:
   Cost of materials to be purchased from Titas
Gas Store existing line to the outlet of the matter. The rates are approximate
and subject to Titas ex-store price and demand note.
| 
   
Sl. No. 
 | 
  
   
Name of items 
 | 
  
   
Quantity 
 | 
  
   
Unite Price 
 | 
  
   
Amount (Tk.) 
 | 
 ||
| 
   
01 
 | 
  
   
6¢¢ M.S
  Pipe API Gr. B/Erw  
 | 
  
   
366
  meter 
 | 
  
   
3200
  P. meter 
 | 
  
   
11,71,200/- 
 | 
 ||
| 
   
02 
 | 
  
   
6¢¢×6¢¢×6¢¢
  Flange Tee  
 | 
  
   
1 No 
 | 
  
   
80,000
  P. Pcs 
 | 
  
   
80,000/- 
 | 
 ||
| 
   
03 
 | 
  
   
6¢¢×400¢ Tap  
 | 
  
   
30 Roll
   
 | 
  
   
12000
  P. Roll 
 | 
  
   
3,60,000/- 
 | 
 ||
| 
   
04 
 | 
  
   
Welding Road Ferograf-10  
 | 
  
   
20 Pac
   
 | 
  
   
1100
  P. Pac 
 | 
  
   
22,000/- 
 | 
 ||
| 
   
05 
 | 
  
   
Primer  
 | 
  
   
16
  Litter/1 Dram 
 | 
  
   
8000
  P. Dram 
 | 
  
   
8,000/- 
 | 
 ||
| 
   
06 
 | 
  
   
6¢¢ Boll
  Valve  
 | 
  
   
2 No 
 | 
  
   
40,000
  P. Pcs 
 | 
  
   
80,000/- 
 | 
 ||
| 
   
07 
 | 
  
   
6¢¢
  Insolating Join  
 | 
  
   
1 No 
 | 
  
   
30000
  P. Pcs 
 | 
  
   
30,000/- 
 | 
 ||
| 
   
08 
 | 
  
   
6¢¢×90°  Elbow  
 | 
  
   
4 No 
 | 
  
   
1200
  P. Pcs 
 | 
  
   
4,800/- 
 | 
 ||
| 
   
09 
 | 
  
   
Parzin Point, Flance, Washa Nut Bolto, etc.  
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
10,000/- 
 | 
 ||
| 
   
Total
  = 
 | 
  
   
17,66,000/- 
 | 
 |||||
| 
   
10 
 | 
  
   
Cost of road cutting permission & hydrolyzing
  boring charge etc.   
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
4,00,000/- 
 | 
 ||
| 
   
11 
 | 
  
   
Cost of labour charge, welding, pipe taping,
  cleaning & office work etc.   
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
6,50,000/- 
 | 
 ||
| 
   
Grand
  Total= 
 | 
  
   
28,16,000/- 
 | 
 |||||
N.B:
The rate of above items may very as per Titas Gas Company Ltd specification.
Yours
faithfully
For:
Bari Enterprise
(Al-Haz Md. Ibrahim Khalil)
To
The
Managing Director
Rahimafrooz,
West
Panisail, Zirani Bazar, Savar, 
Gazipur,
Bangladesh.
Sub:  Estimate for conversion of Gas firing system of your Generator &
Hit temper.  
Part-A:
   Cost of materials to be purchased from Titas
Gas Store existing line to the outlet of the matter. The rates are approximate
and subject to Titas ex-store price and demand note.
| 
   
Sl. No. 
 | 
  
   
Name of items 
 | 
  
   
Quantity 
 | 
  
   
Unite Price 
 | 
  
   
Amount (Tk.) 
 | 
 
| 
   
01 
 | 
  
   
4¢¢ Flance
  Tee  
 | 
  
   
1 No 
 | 
  
   
65000
  P. Pcs 
 | 
  
   
65,000/- 
 | 
 
| 
   
02 
 | 
  
   
4¢¢ API
  pipe grade-B  
 | 
  
   
40
  Feet 
 | 
  
   
850
  P. Feet 
 | 
  
   
34,000/- 
 | 
 
| 
   
03 
 | 
  
   
Cost of road cutting permission & hydrolyzing
  boring charge etc.   
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
4,00,000/- 
 | 
 
| 
   
04 
 | 
  
   
Cost of labour charge, welding, pipe taping,
  cleaning & office work etc.   
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
6,50,000/- 
 | 
 
| 
   
Total= 
 | 
  
   
11,49,000/- 
 | 
 |||
In Word: Eleven Thousand Forty Nine Thousand Taka
Only.
N.B:
The rate of above items may very as per Titas Gas Company Ltd specification.
Yours faithfully
For:
Bari Enterprise
(Al-Haz Md. Ibrahim Khalil)
To
The
Managing Director
Rahimafrooz,
West
Panisail, Zirani Bazar, Savar, 
Gazipur,
Bangladesh.
Sub:  Estimate for conversion of Gas firing system of your Generator &
Hit temper.  
Part-A: Cost of materials to be
purchased from 150/10 PSI Titas Gas Store existing line to the outlet of the
matter. The rates are approximate and subject to Titas ex-store price and
demand note.
| 
   
Sl. No. 
 | 
  
   
Name of items 
 | 
  
   
Quantity 
 | 
  
   
Unite Price 
 | 
  
   
Amount (Tk.) 
 | 
 
| 
   
01 
 | 
  
   
4¢¢ Flance
  Tee  
 | 
  
   
1 No 
 | 
  
   
95000
  P. Pcs 
 | 
  
   
95,000/- 
 | 
 
| 
   
02 
 | 
  
   
4¢¢ API
  pipe grade-B  
 | 
  
   
90
  Feet 
 | 
  
   
850
  P. Feet 
 | 
  
   
76,500/- 
 | 
 
| 
   
03 
 | 
  
   
Cost of road cutting permission & hydrolyzing
  boring charge etc.   
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
4,50,000/- 
 | 
 
| 
   
04 
 | 
  
   
Cost of labour charge, welding, pipe taping,
  cleaning & office work labour etc. 
   
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
6,50,000/- 
 | 
 
| 
   
05 
 | 
  
   
Regulator, Filter, pipe line washing &
  cleaning etc office cost average   
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
4,00,000/- 
 | 
 
| 
   
06 
 | 
  
   
4¢¢ Boll
  Bulb and falnce Nut Bolt washer etc 
 | 
  
   
1 No 
 | 
  
   
80,000
  P. Pcs 
 | 
  
   
80,000/- 
 | 
 
| 
   | 
  
   
Total= 
 | 
  
   
17,51,500/- 
 | 
 ||
In Word: Seventeen Lac Fifty One Thousand Five
Hundred Taka Only.
N.B:
The rate of above items may very as per Titas Gas Company Ltd specification.
Terms
and Conditions: 
01.  All the
works will be carried out as per Titas Gas Specification and direction.
02.  The
above quantities are approximate and subject to actual work basis.
03.    
40% advance to be
paid by the owner against Labour charge at the time of signing of the
Agreement.
04.  3 month
time to be required for completion of the works after approval by the Titas Gas
T & D Company Ltd. Office.
With
thanks and best regards,   
Yours
faithfully
For:
Bari Enterprise
(Al-Haz Md. Ibrahim Khalil)
To
The
Managing Director
Rahimafrooz,
Unit-2,
West
Panisail, Zirani Bazar, Savar, 
Gazipur,
Bangladesh.
Sub:  Estimate for conversion of Gas firing system of your Generator &
Hit temper.  
Part-A:
   Cost of materials to be purchased from Titas
Gas Store existing line to the outlet of the matter. The rates are approximate
and subject to Titas ex-store price and demand note and labor cost.
| 
   
Sl. No. 
 | 
  
   
Name of items 
 | 
  
   
Quantity 
 | 
  
   
Unite Price 
 | 
  
   
Amount (Tk.) 
 | 
 
| 
   
01 
 | 
  
   
4¢¢ Flance
  Tee  
 | 
  
   
1 No 
 | 
  
   
95000
  P. Pcs 
 | 
  
   
95,000/- 
 | 
 
| 
   
02 
 | 
  
   
4¢¢ API
  pipe grade-B  
 | 
  
   
90
  Feet 
 | 
  
   
850
  P. Feet 
 | 
  
   
76,500/- 
 | 
 
| 
   
03 
 | 
  
   
Cost of road cutting permission & hydrolyzing
  boring charge etc.   
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
4,00,000/- 
 | 
 
| 
   
04 
 | 
  
   
Cost of labour charge, welding, pipe taping,
  cleaning & office work etc.   
 | 
  
   
L.S 
 | 
  
   
L.S 
 | 
  
   
6,50,000/- 
 | 
 
| 
   
05 
 | 
  
   
4¢¢ Boll
  Bulb and falnce Nut Bolt washer etc 
 | 
  
   
1 No 
 | 
  
   
80,000
  P. Pcs 
 | 
  
   
80,000/- 
 | 
 
| 
   
In Word: Thirteen Lac Fifteen Thousand Taka Only. 
 | 
  
   
Total= 
 | 
  
   
13,15,000/- 
 | 
 ||
N.B:
The rate of above items may very as per Titas Gas Company Ltd specification.
Terms
and Conditions: 
05.  All the
works will be carried out as per Titas Gas Specification and direction.
06.  The
above quantities are approximate and subject to actual work basis.
07.    
40% advance to be
paid by the owner against Labour charge at the time of signing of the
Agreement.
08.  3 month
time to be required for completion of the works after approval by the Titas Gas
T & D Company Ltd. Office.
With
thanks and best regards,   
Yours
faithfully
For:
Bari Enterprise
(Al-Haz Md. Ibrahim Khalil)