Subject: Estimate for installation of Gas Line for Boiler 6² of 8² dia
Service Line 150 PSI to 15 PSI (Service line 4² line may be extended upto 6² dia
line as per Titas Rules if the load increased otherwise the existing line
remain as usual (Load extension work).
Part-A:
Cost of materials to be procured from Titas
Gas for Titas existing line to inlet of the meter. The rates are approximate
and subject to Titas Ex-store price and demand note.
Sl. No.
|
Name of items
|
Quantity
|
Unite Price
|
Amount (Tk.)
|
01
|
6¢¢ M.S
Pipe API 5L Gr. B. ERW
|
275
meter
|
3250
P. meter
|
8,93,750/-
|
02
|
6¢¢
Flange Tee (Service Tee)
|
01 No
|
2,25,000
P. Pcs
|
2,25,000/-
|
03
|
6¢¢
Flange valve Class 15 ORF
|
04 No
|
85,000
P. Pcs
|
3,40,000/-
|
04
|
6¢¢ Flange
Class 150 RF
|
08 No
|
2,200
P. Pcs
|
17,600/-
|
05
|
6¢¢
Gaskit
|
16 No
|
200
P. Pcs
|
3,200/-
|
06
|
5/8¢¢×3
![]() |
64 No
|
123
P. Pcs
|
8,000/-
|
07
|
6¢¢×900
elbow
|
08 No
|
3000
P. Pcs
|
24,000/-
|
08
|
6¢¢ insulating
joint or kkt
|
01 No
|
1,10,000
P. Pcs
|
1,10,000/-
|
09
|
1¢¢ Plug
& Socket
|
04
Roll
|
300
P. Roll
|
2,400/-
|
10
|
Primer
|
48
Litter
|
200
P. Litter
|
9,600/-
|
11
|
4¢¢ 400¢ Tape
|
25
Roll
|
12,000
P. Pcs
|
3,00,000/-
|
12
|
M.S Valve pit Cover
|
03 No
|
28,000
P. Pcs
|
84,000/-
|
13
|
6¢¢× 6¢¢× 6¢¢ Tee
|
01 No
|
6000
P. Pcs
|
6,000/-
|
Total
=
|
20,20,550/-
|
Contd.
P/2
-2-
N.B:
The above materials cost may be more or less after inspection by the Titas Gas
T & D Co. Ltd.
Part-B:
Cost of internal 15 PSI Gas line
materials from the outlet of the meter in different utilization points (may be
supplied by the customer).
Sl.
No.
|
Name
of Item
|
Quantity
|
Unit
Price
|
Amount
(Tk.)
|
01
|
8¢¢ dia M.S
Pipe API SL Gr. B. ERW
|
305 m
|
2200
P. m
|
6,71,000/-
|
02
|
8¢¢ ´ 900
Elbow
|
08 No
|
3000
|
24,000/-
|
03
|
8¢¢
Flange valve
|
02 No
|
80,000
|
1,60,000/-
|
04
|
8¢¢
Flange
|
04 No
|
2,200
|
8,800/-
|
05
|
3/4¢¢×3
![]() |
64 No
|
123
P. Pcs
|
8,000/-
|
06
|
8¢¢ ´8¢¢´8¢¢
M.s.t
|
02 No
|
6000
|
12,000/-
|
07
|
8¢¢ Gaskit
|
8 No
|
200
P. pcs
|
1,600/-
|
|
|
|
Total
|
8,85,400/-
|
N.B: in is mentioned here that
cost may be more or less at the time of works and excess materials cost to be
vaunted as per market rate if required.
Contd.
P/3
-3-
Part-C:
Cost of labour charge against Part-A (Titas
Existing Line) and Part- B (Internal line) House Line.
01
|
Laying of pipe complete with
trench cutting, poucca/RCC Cutting cleaning, coating, wrapping, normal back
filling etc. as per specification of Titas Gas Company average from 6¢¢ to 8¢¢ dia pipe.
|
|
|
|
02
|
Welding charges or the following:
a)
8¢¢ Butt
Weld
b)
6¢¢ Butt
Weld
|
|
|
|
03
|
Installation charges or the following:
a)
6¢¢
Flange tee weld. (Service tee)
b)
6¢¢
Flange valve fitting and welding
c)
8¢¢ and
6¢¢
Flange valve fitting and welding
d)
6¢¢
elbow weld
|
|
|
|
04
|
Cost of conversion drawings.
|
|
|
|
05
|
Purging/testing with Nitrogen gas or Air to meet
the safety Rules of Titas Gas.
|
|
|
|
06
|
Cost of Road cutting permission from the Road
authority or any other authority or Department to be procured either by the
Contractor or Customer for 6¢¢ dia
main line (cost ot be demanded by the Road authority).
|
Collection
by the customer
|
||
07
|
Construction of Pucca /RCC valve inspection pit
complete with all required materials like bricks, sand, cement, M.S. Rod,
concrete etc. including excavation etc. as per specification of Titas Gas Co.
|
|
|
|
08
|
Overall service charges and office expenses, meter
fitting, R.M. fitting etc. complete.
|
|
|
|
09
|
Cost of carrying charges from Demra Store to your
work site for six (6¢¢)
dia. Total cost with labour charges, truck hire charges and office expenses.
|
17,50,000/-
|
Contd.
P/4
-4-
Grand
Total:
Part-
A : Titas existing line pay
demand note Tk. 20,20,550/-
Part-
B : Internal material costing Tk. 8,41,400/-
Part-
C : Labour Cost Part A & Part B etc. Tk.
17,50,000/-

In
Word: Forty Six Lac Eleven Thousand Nine Hundred Fifty Only.
Terms
and Conditions:
01. All
the works will be carried out as per Titas Specification and direction.
02. The
above quantities are approximate and subject to actual work basis.
03. Titas
security money to be paid as 36,000 cft per hour gas 1/3rd cash
33,45,085 and 2/3rd 66,9170
as bank guarantee boiler for 5 years in favour or Titas Gas System Ltd.