Subject: Estimate for installation of Gas Line for Boiler 6² of 8² dia Service Line 150 PSI to 15 PSI (Service line 4² line may be extended upto 6² dia line as per Titas Rules if the load increased otherwise the existing line remain as usual (Load extension work).  


Part-A:    Cost of materials to be procured from Titas Gas for Titas existing line to inlet of the meter. The rates are approximate and subject to Titas Ex-store price and demand note.

Sl. No.
Name of items
Quantity
Unite Price
Amount (Tk.)
01
6¢¢ M.S Pipe API 5L Gr. B. ERW
275 meter
3250 P. meter
8,93,750/-
02
6¢¢ Flange Tee (Service Tee)
01 No
2,25,000 P. Pcs
2,25,000/-
03
6¢¢ Flange valve Class 15 ORF
04 No
85,000 P. Pcs
3,40,000/-
04
6¢¢ Flange Class 150 RF
08 No
2,200 P. Pcs
17,600/-
05
6¢¢ Gaskit
16 No
200 P. Pcs
3,200/-
06
5/8¢¢×3¢¢Stud. Nut bolts
64 No
123 P. Pcs
8,000/-
07
6¢¢×900 elbow
08 No
3000 P. Pcs
24,000/-
08
6¢¢ insulating joint or kkt
01 No
1,10,000 P. Pcs
1,10,000/-
09
1¢¢ Plug & Socket
04 Roll
300 P. Roll
2,400/-
10
Primer
48 Litter
200 P. Litter
9,600/-
11
4¢¢ 400¢ Tape
25 Roll
12,000 P. Pcs
3,00,000/-
12
M.S Valve pit Cover
03 No
28,000 P. Pcs
84,000/-
13
6¢¢× 6¢¢× 6¢¢ Tee
01 No
6000 P. Pcs
6,000/-
Total =
20,20,550/-

Contd. P/2
-2-

N.B: The above materials cost may be more or less after inspection by the Titas Gas T & D Co. Ltd.


Part-B:    Cost of internal 15 PSI Gas line materials from the outlet of the meter in different utilization points (may be supplied by the customer).

Sl. No.
Name of Item
Quantity
Unit Price
Amount (Tk.)
01
8¢¢ dia M.S Pipe API SL Gr. B. ERW
305 m
2200 P. m
6,71,000/-
02
8¢¢ ´ 900 Elbow
08 No
3000
24,000/-
03
8¢¢ Flange valve 
02 No
80,000
1,60,000/-
04
8¢¢ Flange
04 No
2,200
8,800/-
05
3/4¢¢×3¢¢ Nut bolts & Washers
64 No
123 P. Pcs
8,000/-
06
8¢¢ ´8¢¢´8¢¢ M.s.t
02 No
6000
12,000/-
07
8¢¢  Gaskit
8 No
200 P. pcs
1,600/-



Total
8,85,400/-

N.B: in is mentioned here that cost may be more or less at the time of works and excess materials cost to be vaunted as per market rate if required.


Contd. P/3


-3-

Part-C:    Cost of labour charge against Part-A (Titas Existing Line) and Part- B (Internal line) House Line. 

01
Laying of pipe complete with trench cutting, poucca/RCC Cutting cleaning, coating, wrapping, normal back filling etc. as per specification of Titas Gas Company average from 6¢¢ to 8¢¢ dia pipe.



02
Welding charges or the following:
a)      8¢¢ Butt Weld
b)       6¢¢ Butt Weld



03
Installation charges or the following:
a)      6¢¢ Flange tee weld. (Service tee)
b)      6¢¢ Flange valve fitting and welding
c)      8¢¢ and 6¢¢ Flange valve fitting and welding
d)      6¢¢ elbow weld



04
Cost of conversion drawings.



05
Purging/testing with Nitrogen gas or Air to meet the safety Rules of Titas Gas.



06
Cost of Road cutting permission from the Road authority or any other authority or Department to be procured either by the Contractor or Customer for 6¢¢ dia main line (cost ot be demanded by the Road authority).
Collection by the customer
07
Construction of Pucca /RCC valve inspection pit complete with all required materials like bricks, sand, cement, M.S. Rod, concrete etc. including excavation etc. as per specification of Titas Gas Co.



08
Overall service charges and office expenses, meter fitting, R.M. fitting etc. complete.



09
Cost of carrying charges from Demra Store to your work site for six  (6¢¢) dia. Total cost with labour charges, truck hire charges and office expenses.
17,50,000/-

Contd. P/4


-4-


Grand Total:
Part- A             : Titas existing line pay demand note               Tk.   20,20,550/-
Part- B : Internal material costing                                 Tk.   8,41,400/-           
Part- C : Labour Cost Part A & Part B etc.                   Tk.   17,50,000/-                     
                                                                                    Tk.   46,11,950/-


In Word: Forty Six Lac Eleven Thousand Nine Hundred Fifty Only.



Terms and Conditions:

01.  All the works will be carried out as per Titas Specification and direction.
02.  The above quantities are approximate and subject to actual work basis.
03.  Titas security money to be paid as 36,000 cft per hour gas 1/3rd cash 33,45,085 and 2/3rd  66,9170 as bank guarantee boiler for 5 years in favour or Titas Gas System Ltd.

With thanks and best regards,  